Our site construction team had reached 90% progress of the total project site installation work. Was last week the team was working on the following:
– Carry out casting the base and Necks for PROVER skid foundations.
– Carry out installing wood shuttering of valves foundation grout work at all areas.
– Carry out pouring concrete and grout for valves foundations at all area.
– Carry out the valves supports fabricatio and painting.
– Carry out sun shad Fabrication and painting.
– Carry out installing work station at control room.