Supply and Installation of Custody Transfer Flow meters

Client: ARC, AZZAWYIA Oil Refinery Company Date: week 02 - 2018 Rida T.S is carrying on with the foundation work of system prover base for their clients ARC, Azzawyia Oil Refinery Company - Wood shuttering work for prover foundation base. - Setting up RIDA’s new construction area at ARC plant. [...]

2018-03-02T15:59:09+00:00

Supply and Installation of Custody Transfer Flow-meters

Client: ARC, AZZAWYIA Oil Refinery Company Date: week 50 - 2017 Our site construction team had reached 90% progress of the total project site installation work. Was last week the team was working on the following: - Carry out casting the base and Necks for PROVER skid foundations. - Carry [...]