Our company |
Work |
SOC On-Site Project |
SOC on-site Project
Sirte Oil Company
Brega Terminal
– Dismantling the valves
– Splitting Valves bodies
– Removing of rings
– Replace the body/flange gasket
– Assemble the valves parts back together
– Erecting valves back to line
– Splitting Valves bodies
– Removing of rings
– Replace the body/flange gasket
– Assemble the valves parts back together
– Erecting valves back to line
The Job was done accompanied by PROVALVE Engineer to carry out a maintenance work “site and workshop” for 15 DBBV double block bleed valves